New City Hall & Library

The City began construction on a new City Hall and Library in March 2024. Completion of this facility is expected at the end of 2025. Below is a photo and video timeline of the project. Photos and videos are posted chronologically with the newest postings at the top of the page. Renderings of the outside and inside of the facility are at the bottom of the page. 

August 11, 2025 - Solar Panels Installed

The City partnered with the Blue Sky program by Rocky Mountain Power to add solar panels to the roof, giving us the ability to offset the cost of power for this building. We are excited to work with Rocky Mountain Power to help protect the environment and save money. 


October 9, 2024 - Staff Site Visit of the Second and Third Floor

Library From The South


September 13, 2024 - Topping Off Ceremony

August 26, 2024 - First Beams Installed

Beams up at New City Hall

June 10, 2024 - Cement Footing Poured

City Hall Cement Footing Poured

March 18, 2024 - Groundbreaking

20240318_160229

February 21, 2024 - Community Open House - PDF of Open House Images 

City Hall South Side

This project was made possible with funding support from Rocky Mountain Power's Blue Sky program customers.